discover more
Arrow down

Scottish Water Howden

Total System Size:
1.2MW + 1.8MWh DC coupled BESS

Annual Generation:
932,630kWh

PV Modules:
2,112 DMEGC 550W Modules

Inverter:
4 Solinteg Inverters

Carbon Offset Value (annual):
169 tons

Scottish Water's First Solar and Battery Storage at a Water Treatment Works

Emtec Energy was selected by Scottish Water for a landmark renewable energy project at the Howden Water Treatment Works in Selkirk, marking the utility’s first integration of solar power with battery storage at a water treatment facility. This project sets a new benchmark for sustainability in the sector and showcases Emtec Energy's expertise in delivering complex, innovative energy solutions.

The installation involved a 1.2MW Solar PV system paired with a 1.8MWh DC battery storage unit, featuring 2,112 solar panels and four 50kW inverters. Emtec Energy designed the system to optimize energy generation while avoiding the typical costs and delays of G100 device installation and Distribution Network Operator (DNO) witness testing. This streamlined approach reduced both project costs and timelines, ensuring seamless integration. Notably, the integration of the battery storage system, which fully complies with DNO specifications, enabled the project to avoid grid connection costs of approximately £2.3 million for the client, delivering substantial financial savings.

A significant challenge was the grid's initial limitation of 200kW of inverter power. Emtec Energy addressed this by deploying a 1.8MWh DC battery storage system with a 200kW inverter, which allowed the system size to be scaled up to 1.2MWp. This approach maximized energy generation and improved the site’s carbon offset potential. By adopting a DC-coupled battery storage method, Emtec eliminated energy losses common in AC-DC-AC conversions, enhancing system efficiency and allowing Scottish Water to store cheaper off-peak energy for use during peak times, thereby reducing operational costs.

During the project’s late design stages, Emtec Energy encountered an environmental challenge due to the site’s location within a well field and borehole area. To prevent any risk of contamination, ground penetration was not an option. In response, Emtec changed the piling method securing the super structure with concrete ballast blocks, which allowed for zero ground penetration. This innovative design preserved the site's environmental integrity and ensured full compliance with all regulations. Additionally, all on-site machinery was powered by food-grade HVO biodiesel, and hydraulic machines were selected for their minimal environmental impact.

The site's floodplain location required Emtec to design the system with elevated ground clearance and use surface-run AC and DC cables on containment structures rather than burying them. This mitigated flood risks and enhanced the installation's durability and safety.

The result is a highly efficient solar and battery storage system that continuously supplies 200kW of power to the Howden Water Treatment Works, significantly enhancing operational efficiency and shortening the return on investment for Scottish Water. This project underscores Emtec Energy’s ability to deliver sustainable energy solutions in environmentally sensitive settings, reinforcing their position as a leader in the renewable energy sector.

Chris Clark, Director at Emtec Energy, highlighted the project’s success, stating, “The solar and battery energy storage system at Howden is a significant achievement for us and underscores our commitment to advancing renewable energy solutions. We’ve delivered a high-efficiency system that meets the site’s stringent requirements and aligns with our vision of reducing carbon footprints across Scotland. This project is a testament to the innovative thinking and meticulous planning we bring to every project, and we’re honoured to have partnered with Scottish Water Horizons.”

Client

Scottish Water

Sector

Water Utilities

location

Selkirk

"Having worked on three separate renewables projects with Emtec Energy, I can confidently say that their site supervision is the best I've encountered. Their supervisors are exceptionally well-trained and consistently available, ensuring that everything runs smoothly on site. The project management team is equally impressive, providing prompt responses and resolving issues quickly whenever they arise.

On our Howden solar power and battery energy storage project, Emtec Energy demonstrated their ability to adapt efficiently, implementing a late-stage redesign due to water quality concerns with remarkable speed and precision. This was achieved at no additional cost and without any delays to the project's timeline.”

Alan Mearns, Project Manager, Scottish Water Horizons

Gallery

Video

Environmental Impact

Tree icon
2,806 trees
Carbon reduction equivalent to planting 2,806 trees grown for 10 years
Co2 cloud icon
169 tons
Carbon Offset Value 169 tons
Mobile phone icon
11.2 million
Equivalent of 11.2 million fully charged smartphones

related case studies

Find out more

Careers

Opportunities at Emtec

learn more
Button arrow

get in touch

How can we help?

For general enquiries please contact us or click here to contact your nearest office.